London ‘super sewer’ boss awarded £600,000 pay rise despite £100m cost overrun | Water industry
The chief executive of the London “super sewer” project has been awarded a £600,000 pay rise even as the firm revealed that the total cost had risen by £100m.
Andy Mitchell received pay of £2.5m for the year to March 2025, up from £1.9m the year before, according to accounts published by the Thames Tideway tunnel builder, Bazalgette Tunnel Limited.
The Tideway project is seen as a crucial upgrade to London’s sewage system, which had been reliant on sewers designed during the reign of Queen Victoria by Joseph Bazalgette. The sewer was a response to the “Great Stink” of 1858.
London’s population has more than tripled since then, and water pollution has again become politically salient because of widespread disgust about sewage leaking into Britain’s rivers and seas. That has led to close scrutiny of executive pay in the water industry, which is run as a series of privately owned monopolies.
The 15.5-mile sewage tunnel runs mostly under the Thames. It was originally due to be completed in 2024 but was delayed by the Covid pandemic. The total cost has now reached £4.6bn, the Tideway company said, up from £4.5bn reported last year and more than £1bn over the initial £3.5bn estimate.
Mitchell’s pay increase was mostly driven by £500,000 added to his “retention bonus”, which hit £1.5m. He received a base salary of £550,000, plus an extra bonus of £423,000 and unnamed “benefits” and pension contributions worth £21,000.
However, his total pay was lower than the £2.7m he received in 2023. Mitchell has previously worked on projects including Hong Kong airport and the Thameslink and Elizabeth rail lines in London.
The scale of the rewards on offer have been criticised, given that the Tideway company is funded by mandatory additions to customer bills.
Luke Hildyard, the director of the High Pay Centre, a thinktank that tracks executive pay, said: “The culture of very high top pay and extreme concentration of income at the top of the distribution in the UK is a real problem for living standards. If so much of the wealth generated by our economy is captured by a tiny elite, it becomes much harder to improve life for everybody else.
“We need a plan to address this issue and more reasonable pay levels for quasi public service roles like this would be an obvious place to start. No doubt running Tideway is a challenging role, but it also carries considerable prestige and other non-financial rewards. It seems likely that a competent project manager could have been found without requiring such extravagant executive pay awards.”
after newsletter promotion
Matthew Duncan, the Tideway company’s finance director, received pay worth £1.7m, up from £1.3m last year.
A Tideway spokesperson said: “The Thames Tideway tunnel is a world-class infrastructure project and one of the most complex in the UK. It has been delivered within the original timetable and within the cost range estimate for bill payers outlined before we started work, at around £25 a year. After nine years of construction and the work of around 25,000 people, it is now operational, protecting the River Thames from millions of tonnes of sewage pollution.
“Tideway’s remuneration reflects the complexity of the engineering challenge and takes account of schedule, cost, health and safety and sustainability goals. The increase is largely due to the payment of a long-term retention incentive that has supported consistent leadership and the successful delivery of this vital infrastructure project.”
Business
UK bosses to be banned from using NDAs to cover up misconduct at work | Employment law
Bosses in the UK will be banned from using non-disclosure agreements to silence employees who have suffered harassment and discrimination in the workplace as part of the government’s overhaul of workers’ rights.
Ministers will on Monday night table amendments to the government’s employment rights bill to prohibit the widespread practice of using legally enforceable NDAs to conceal unacceptable behaviour at work.
If passed, the rules would mean any future confidentiality clauses in settlement agreements that sought to prevent a worker speaking about an allegation of harassment – including sexual harassment – or discrimination would be null and void.
They would also allow victims to speak freely about their experiences, while any witnesses – including employers – would be able to call out poor conduct and publicly support victims without the threat of being sued.
The changes being introduced to the bill, due to return to the Lords next week, would not affect NDAs for legitimate commercial use, such as commercially sensitive information or intellectual property in business transactions.
But they would create one of the toughest protection regimes in the world, giving millions of workers, including those in low-paid jobs, more confidence that inappropriate behaviour in the workplace would be dealt with.
After years of campaigning by activists, ministers have looked beyond high-profile cases linked to the #MeToo movement to address concerns about workers in regular employment who may not have the means or confidence to pursue their employers through the courts to challenge “gagging orders”.
Announcing the change, Angela Rayner, the deputy prime minister, said: “Victims and witnesses of harassment and discrimination should never be silenced. As the Guardian has reported on widely, this is not an issue confined to high-profile individuals or the most powerful organisations.
“The use of NDAs to cover up abuse and harassment is growing – and sadly amongst those in low-income or insecure employment across multiple industries and workplaces.
“This cannot go on. That is why we are stamping out this practice and taking action to ban any NDAs used for this purpose. My message is clear: no one should suffer in silence and we will back workers and give survivors the voice that they deserve.”
The legislation represents the biggest overhaul of workers’ rights in a generation, introducing day one rights, establishing collective bargaining bodies in vital sectors and strengthening family-friendly entitlements, as well as going further on bereavement leave and tackling “fire-and-rehire”.
Over time NDAs have become the default solution for many organisations, corporations and public bodies to settle cases including sexual misconduct, racism, and pregnancy discrimination.
Their original purpose was to protect intellectual property or other commercial or sensitive information, but reports have shown they have become commonly used to prevent people speaking out about horrific experiences in the workplace.
There have been many high-profile cases of NDAs being used to prevent victims from speaking about crimes, often forcing women and vulnerable individuals to feel stuck in unwanted situations, through fear or desperation.
They have proliferated especially in lower-income, insecure employment including sectors such as retail, hospitality and accommodation, with non-disparagement clauses also typically attached.
A report by the Chartered Institute of Personnel and Development (CIPD) last year found the use of NDAs was relatively common, with 22% of respondents to a survey of 2,000 employers saying their organisation used them when dealing with allegations of sexual harassment.
In contrast, 44% said they did not use NDAs in this way and a further 34% did not know, highlighting that awareness around their use in some organisations may be low.
The CIPD also found that most employers would not strongly object to the removal of NDAs in the workplace. Nearly half (48%) of employers would support a ban, with just 18% opposing, while 20% were ambivalent, and a further 14% did not know.
Zelda Perkins, a former PA to Harvey Weinstein who spearheads the campaign group Can’t Buy My Silence, said of the government’s plans: “This is a huge milestone, for years we’ve heard empty promises from governments whilst victims have continued to be silenced.
“To see this government accept the need for nationwide legal change shows that they have listened and understood the abuse of power taking place.
“Above all though, this victory belongs to the people who broke their NDAs, who risked everything to speak the truth when they were told they couldn’t. Without their courage, none of this would be happening.
“This is not over yet and we will continue to focus closely on this to ensure the regulations are watertight and no one can be forced into silence again. If what is promised at this stage becomes reality, then the UK will be leading the world in protecting not only workers but the integrity of the law.”
Louise Haigh, a former cabinet minister, said: “Victims of harassment and discrimination have been forced to suffer in silence for too long. Today’s announcement will mean that bad employers can no longer hide behind legal practices that cover up their wrongdoing and prevent victims from getting justice.”
Legislative changes have already been made in Ireland, Canada and the US so that NDAs cannot prohibit disclosure of sexual harassment, discrimination or bullying without it being the expressed wish of the employee.
A landmark survey of sexual harassment at work has found that one in four women have suffered work-related sexual assault.
Britain’s largest trade union, Unite, polled approximately 300,000 female members on whether they had experienced sexual harassment at work, travelling to work or from a colleague in or out of work hours.
Of the 6,615 respondents, 25% said they had been sexually assaulted and 43% had been inappropriately touched. More than 3,000 said they had been the recipient of sexually offensive jokes and/or experienced unwanted flirting, gesturing or sexual remarks.
And 28% had been shared or shown pornographic images by a manager, colleague or third party, while 8% had been a victim of sexual coercion – when a person pressures, tricks, threatens or manipulates someone into engaging in sexual activity without genuine consent – at work.
While the perpetrator in the bulk of these incidents was a member of public in the workplace, such as a patient or a passenger, 3% said they had been sexually assaulted by a manager and 6% by a colleague.
Business
Trump steps up trade wars with 25% tariffs on Japan and South Korea | Trump tariffs
Donald Trump unveiled plans to step up his trade wars on Monday, announcing Japan and South Korea will soon face US tariffs of 25% in a significant escalation of his controversial economic strategy.
The US president, who indicated that he would notify as many as as 15 countries of new, higher rates on Monday, posted copies of letters addressed to the leaders of Japan and South Korea on social media. Trump said the rates were set to go into effect 1 August.
The letters were largely identical and informed the leaders that there will be no tariffs if their countries “decide to build or manufacture product within the United States”.
Trump also threatened higher tariffs if the countries place additional tariffs on US exports. “If for any reason you decide to raise your tariffs, then, whatever the number you choose to raise them by, will be added onto that 25% we charge,” he wrote.
Trump initially announced a slate of so-called reciprocal tariffs in April, on what the White House dubbed “liberation day”, with some countries facing rates as high as 50%
While he paused those tariffs for 90 days amid market turmoil, this reprieve is due to expire on Wednesday 9 July.
Trump officials initially suggested they would strike dozens of deals with key economies during the pause, but have since indicated that they would use an extension to continue talks.
The treasury secretary, Scott Bessent, said last month the administration was aiming to wrap up negotiations by Labor Day on 1 September.
The US has so far settled deals with three countries: the UK, China and Vietnam, and Bessent said there were over a dozen countries the US is still trying to negotiate with.
The new August deadline for countries without a deal amounts to a further three-week reprieve, but also triggers fresh uncertainty for importers because of the lack of clarity around the tariffs.
As the July deadline has approached, Trump’s officials have been racing to broker deals. Over the weekend, one European diplomat said the US may have to “show muscle if the deal is not good enough”.
The White House also reached an impasse in negotiations with Japan, despite initial optimism. Trump on Friday said it is “much easier to send a letter” and that the offers are “take it or leave it”.
On Wall Street, the benchmark S&P 500 sank by almost 0.9% after Trump posted his first letters.
Though the US stock market has largely recovered from the uncertainty around Trump’s trade war, the US dollar still remains weakened after months of trade fights. At the beginning of this year, the dollar had its worst six months in over 50 years, falling 10.8% since the start of 2025.
Business
Goods from Japan and South Korea hit with 25% levy
The US plans to impose a 25% tax on products entering the country from South Korea and Japan on 1 August, President Donald Trump has said.
He announced the tariffs in a post on social media, sharing letters he said had been sent to leaders of the two countries.
The White House has said it expects to send similar messages to dozens of countries in coming days as the 90-day pause it placed on some of its most aggressive tariffs is set to expire.
The first two letters suggest that Trump remains committed to his initial push for tariffs, with little change from the rates announced in April.
At that time, he said he was looking to hit goods from Japan with duties of 24% and charge a 25% on products made in South Korea.
Those tariffs were included in a bigger “Liberation Day” announcement, which imposed tariffs on goods from countries around the world.
After outcry and turmoil on financial markets following the initial tariffs announcement, Trump suspended some of the import taxes to allow for talks. That deadline is set to expire on 9 July.
On Monday, Treasury Secretary Scott Bessent said he expected “a busy couple of days”.
“We’ve had a lot of people change their tune in terms of negotiations. So my mailbox was full last night with a lot of new offers, a lot of new proposals,” he told US business broadcaster CNBC.
-
Funding & Business7 days ago
Kayak and Expedia race to build AI travel agents that turn social posts into itineraries
-
Jobs & Careers7 days ago
Mumbai-based Perplexity Alternative Has 60k+ Users Without Funding
-
Mergers & Acquisitions6 days ago
Donald Trump suggests US government review subsidies to Elon Musk’s companies
-
Funding & Business6 days ago
Rethinking Venture Capital’s Talent Pipeline
-
Jobs & Careers6 days ago
Why Agentic AI Isn’t Pure Hype (And What Skeptics Aren’t Seeing Yet)
-
Funding & Business4 days ago
Sakana AI’s TreeQuest: Deploy multi-model teams that outperform individual LLMs by 30%
-
Funding & Business7 days ago
From chatbots to collaborators: How AI agents are reshaping enterprise work
-
Jobs & Careers6 days ago
Astrophel Aerospace Raises ₹6.84 Crore to Build Reusable Launch Vehicle
-
Funding & Business6 days ago
Europe’s Most Ambitious Startups Aren’t Becoming Global; They’re Starting That Way
-
Jobs & Careers4 days ago
Ilya Sutskever Takes Over as CEO of Safe Superintelligence After Daniel Gross’s Exit